Surat Lignite Power Plant (Unit 3 & 4)

Factsheet

Capacity 250 MW
Type Lignite based Power Plant
Project Cost N/A
Fuel Lignite Coal
Fuel Source Lignite as fuel from captive mine
Plant Configuration 2 x 125 MW with Circulating Fluidized Bed Combustion (CFBC) Boilers and STGs
Commissioned In April, 2010
Status Independent Power Producer (IPP) - Supplies power to GUVNL through Power Purchase Agreement
Location Surat Lignite Power Plant

Plant Performance

Particulars Financial Year Q1 ending on
2014-15 2015-16 30.06.15 30.06.16
Availability Factor (%) 89.17 75.88 91.91 88.96
PLF (%) 84.09 65.61 80.56 86.57
Generation (MU) 1841.638 1440.694 439.857 472.659